Framing is the part of a build that people remember. The foundation sits there for weeks looking like nothing, and then one Monday a lumber truck shows up and by Friday you can walk through your kitchen. It also raises the most questions, because it moves fast. Here is how a typical single-family house in the Sevier Valley goes, week by week, so you know what you are looking at.
This assumes an ordinary one or two story house with a truss roof. A walkout basement, a stick-framed roof, or a January start will stretch it, and we will tell you where your house lands when we bid it.
Before the crew shows up
We do not start until a few things are true. The foundation has cured and the anchor bolts are where the plans say they are. The lot is graded so the lumber truck and a boom truck can get in without sinking. Power is on site, either a temporary pole or a generator. The lumber package has been delivered from the yard and stacked where it will not be in the way of the forklift.
If you are building, this is the week to make sure your designer has sent the final plan set and the engineering. We frame to the sheets we have, and we have seen more than one job stall because a revised sheet was sitting in someone's inbox.
Week one: floor and first-floor walls
On a crawl space or basement house, the first day or two go to the floor system. We set the sill plate on foam sealer, roll out the joists, hang the rim, and glue and nail the subfloor. When you come by Tuesday evening you will have a flat deck to stand on and not much else.
The rest of the week is walls. We snap lines on the deck, build each wall flat, then stand it up, brace it, and plumb it. Exterior walls go up first, then interior bearing walls, then the rest of the partitions. By Friday the first floor is a maze you can walk through, and this is the point where most homeowners say the rooms look small. They always look small without drywall and with no ceiling. Wait a week.
Week two: second floor or ceiling, then trusses
On a two story house, week two repeats week one on top of the first floor: joists, subfloor, walls. On a single story, we go straight to the ceiling and roof.
Truss day is the one to come watch. The trusses arrive on a flatbed, a crane or boom truck sets them one at a time, and the crew spaces, plumbs and braces each one as it lands. A plain gable roof can be set in a day. Hips, valleys, and vaulted great rooms take longer. Wind matters here. If a Sevier Valley afternoon is gusting hard enough to swing a truss, we wait, because a truss that comes down takes the braced ones with it.
Week three: sheathing and drying in
With the roof framed, the goal is to get the house dried in. Roof sheathing goes on first, then fascia and sub-fascia, then the exterior wall sheathing if it was not done when the walls were flat. House wrap and the window and door openings follow. We cut and flash the openings ourselves, and if we are installing your windows, they usually go in this week or the next.
Once the roof deck and wrap are on, rain and snow stop being an emergency. This is the milestone that lets the roofer, the siding crew and the mechanical trades get scheduled, so if you are managing your own build, now is when to lock in those dates.
Week four: backing, blocking and the inspection
The last week is the quiet one. The crew works through the inside of the house adding the things nobody sees: backing for cabinets, towel bars, handrails and TV mounts; fire blocking; blocking for drywall at corners and ceilings; the hold-downs, straps and hangers from the engineered sheets. Stairs usually get built now.
Then we call the Richfield building department, or Sevier County if you are outside city limits, for the framing inspection. The inspector checks the structure against the stamped plans, the hardware against the engineering, and the nailing on the shear walls. If something needs fixing, we fix it and call for a reinspection. Passing framing is what releases the plumber, electrician and HVAC crew to start rough-in.
What you can do to keep it moving
A few things make a real difference. Have the plans and engineering final before we start. Make your window and door selections early, because lead times are longer than people expect. Keep the driveway and the area around the house clear so deliveries can land. And if you want to change something, say it the week before, not the day the wall goes up. A moved doorway costs almost nothing on paper and a few hundred dollars once it is framed.