If you have ever held two framing bids side by side and wondered why one is $9,000 higher, the answer is usually not that one framer is greedy. It is that they bid two different jobs. One included the sheathing, the other assumed you would buy it. One priced the garage, the other stopped at the house. Until you know what is inside each number, you cannot compare them.
Here is what we put in ours, and what you should look for in anyone's.
The plans it is based on
A bid should name the plan set and the revision date. Plans change. If your designer sends out a new sheet with a taller plate height or a bigger header over the great room, and the bid was written against the old one, that difference shows up later as a change order. We write the plan date on every bid for this reason.
Scope, line by line
At minimum, a framing bid should say whether it includes:
- Floor systems. Joists, rim, subfloor, glue and fasteners. On a crawl space or basement house this is a real chunk of the labor.
- Exterior and interior walls. Studs, plates, headers, blocking, and the backing for cabinets, towel bars and TV mounts. Backing is the thing that gets skipped and then costs you a drywall patch.
- Sheathing and house wrap. Some framers sheathe, some do not. Some wrap, some leave it to the siding crew. Ask.
- Roof. Trusses set and braced, or stick framed? Fascia and sub-fascia? Roof sheathing? Each of those is a separate yes or no.
- Stairs, decks and porches. Often bid separately. Make sure they are somewhere.
- Windows and exterior doors. We install them, because we frame the openings and would rather own the fit. Not every framer does.
Materials: who buys them
A labor-only bid looks cheaper than a labor-and-materials bid by exactly the cost of the lumber. That is not a savings. Ask whether the number includes material, and if it does, ask whether the lumber package was priced from a takeoff of your plans or from a square-foot guess. A real takeoff from the lumberyard is what you want.
Engineering and hardware
Hold-downs, straps, hangers and the Simpson hardware called out on the engineered sheets add up. A bid that does not mention hardware either has it buried in the number or has not read the engineering yet. Either way, ask.
Timeline
How many weeks from the day the foundation is ready, and what has to be true for the crew to start? Concrete cured, lumber delivered, power on site, lot graded so a boom truck can get in. A good framer will tell you the start conditions up front, because a crew that shows up to a site that is not ready costs everyone a day.
What it should not include
Watch for round numbers with no breakdown, bids with no plan date, and "to be determined" on anything structural. And be wary of a number that is far below the others. In our experience that framer either missed something or plans to find it later.
How we do it
Our bids are itemized by the sections above, priced from a lumberyard takeoff of your actual plans, with the plan revision date written on the first page. If something is excluded, it is listed as excluded so you are not guessing. If you would like a bid like that, send us your plans and we will get back to you within a couple of business days.